Lt. Gen. Andrew J. Gebara, deputy chief of staff for strategic deterrence and nuclear integration, said the B-52's new radar will soon enter flight testing and is “turning a corner” after a cost overrun triggered a notification to Congress and program review earlier this year. ...
B-52 radar modernization program
The B-52 Radar Modernization Program has incurred a Nunn-McCurdy breach, with a cost estimate increase of more than 15 percent, the Air Force said. A breach of that magnitude won’t require the Secretary of Defense to certify the program as critical to national defense, but ...
Initial operational capability for the B-52J—the new designation for the bomber after extensive re-engining and upgrade programs—won’t be achieved until 2033. The three-year delay is due to issues both with its new engines and new radar, the Government Accountability Office said in a new report.