The technicians at Warner Robins Air Logistics Center at Robins AFB, Ga., completed routine depot maintenance for C-5 #87040 in just 159 days, beating the previous record by 12 days. What’s more, a year ago, the same process took 200 days. For the most recent Galaxy, the Robins team used new project management software called Concerto, which gave them a visual depiction of the aircraft, the tasks, and status of each task—part of the process called critical chain project management. David Mann, C-5 Production Section chief, said the 160-day flow rate will be maintained for both C-5A and C-5B aircraft despite the older A-model’s demands for more man hours, thanks to new techniques, management, and the work ethic of the depot.
The Air Force displayed all the firepower it has amassed on Okinawa in an unusually diverse show of force this week. IIn a May 6 “Elephant Walk,” Kadena Air Base showcased 24 F-35A Lightning II stealth fighters, eight F-15E Strike Eagles; two U.S. Army Patriot anti-missile batteries near the runway; and…